A project manager is calculating work forecasts. The manager's team completed of a job in 16 days. At this rate, the
manager says that the team completed of the project each day.
What was the manager's error?
O The manager is correct. There was no error.
O The manager divided by 16 instead of dividing
by 16.
O The manager divided 16 by
instead of dividing
by 16.
O The manager divided 16 by
instead of multiplying 16 by
O The manager divided by 16 instead of multiplying 16 by