Find the earliest completion times for order‑requirement digraphs (a) and (b).

——————————————————

Find the critical path for digraph (a).


A. T2T5T7


B. T2T4T5T7


C. T1T3T5T7


D. T3T5T7


E. T1T4T7

——————————————————

Find the critical path for digraph (b).


A. T3T5T7


B. T2T4T5T7


C. T2T5T7


D. T1T3T5T7


E. T1T3T5T8


F. T1T4T7