emilyj2norris emilyj2norris 06-11-2022 Mathematics contestada To compleate a task in 16 days a company needs 5 workers each working 6 hours per day The company decides to have 8 people each working 4 hours per day Assuming that each person works at the same rate How many days will the task take to complete?