Alpha Industries is considering a project with an initial cost of $8.2 million. The project will produce cash inflows of $1.93 million
per year for 6 years. The project has the same risk as the firm. The firm has a pretax cost of debt of 5.67 percent and a cost of
equity of 11.31 percent. The debt-equity ratio is .62 and the tax rate is 24 percent. What is the net present value of the project?
O $553,990
O $498.591
O $576,150
O $474,849
O $418.860