Use the following project status information to calculate each of the requested EVM numbers below (a-i). The project status is reported at the end of week 13.
Task
Budget Cost
Budget Duration
Status as of Week 13
A
$5,000
2 weeks
100 percent complete, $5,000
B
$8,500
3 weeks
100 percent complete, $9,000
C
$15,000
4 weeks
75 percent complete, $14,000
D
$10,000
4 weeks
50 percent complete, $9,000
E
$12,000
4 weeks
Not started
F
$15,000
5 weeks
Not started
a. Planned value
b. Actual cost
c. Cost variance
d. Schedule variance
e. Cost performance index
f. Schedule performance index
g. Budget at completion
h. Estimate to complete
i. Estimate at completion