17

The fixed costs of your project are $100,000. The variable costs of the project are $1,500 per day. How much more would the project cost if it finishes 25 days late?

A

$100,000

B

$101,500

C

$37,500

D

$137,500

-

Which of the following statements about forward passes it true?

A

It is used to calculate the earliest possible starts for each project phase.

B

It is used to calculate the critical path duration of the project.

C

It is used to calculate durations for each activity.

D

It is used to calculate late starts and finishes for each activity.