Northcutt manufactures high-end racing bikes and is looking for a source of gear sprocket sets. Northcutt would need 1,800 sets a month. Supplier A is a domestic firm, and Suppliers B and C are located overseas. Cost information for the suppliers is as follows: - Supplier A-Price of $120 per set, plus packing cost of $1.50 per set. Total inland freight costs for all 1,800 units would be $900 per month. - Supplier B-Price of $54 per set, plus packing cost of $5.00 per set. International transportation costs would total $3,300 per month, while total inland freight costs would be $750 per month. - Supplier C-Price of $142 per set, plus packing cost of $2.00 per set. International transportation costs would total $5,500 per month, while total inland freight costs would be $850 per month.Please find the total landed cost per unit for Supplier C = $______ (round answer to two decimals)
& The total landed cost per month for Supplier C = $________ (enter answer as a whole number)