A particular machine has a loading time of 150 hours in a particular 7 day period. Changeovers and set-ups take an average of 15 hours, and breakdown failures average 5 hours every 7 days. During the time when the machine is running, it averages 92% of its rated speed. 3% of the parts processed by the machine were subsequently found to be defective in some way. All the data is outlined in Table 5.0. Determine the following Valuable operating Time (h's) Overall Equipment Effectiveness (h's) Comment briefly as to how Engineering might assist in improving the competitiveness of this operation?