: Additional Sample Problems on Capacity Planning XYZ company is producing a solar panel for street lighting which is composed of 80 solar cells. The company has 10 solar tabber and stinger machines at any given time. The solar tabber and stringer machines are an equipment that allow to solder and assemble the cells together in order to compose the photovoltaic cell at the rate of 50pcs per hour. The man machine ratio is 1:1. At present the company has 6 technicians per shift and they are working 3 shifts in a day with 75- minute break. They have 5 working days per week and 4 weeks in a month. How much panels can they produce in one month? n BA