Your company is considering submitting a bid on a major project . You determine that the expected completion time 65 wee and the standard deviation is 12 weeks . It is assumed that the normal distribution applies . You wish to set the due date for the proje such that there is an 90 percent chance that the project will be finished by this time . What due date should be set ? ( pick the closes value to your computations ):
65.0
166.4
77.00
80.36
Not enough information