2.2 Marcus is required to address the following:
2.2.1 What options would Marcus have to shorten the duration of the project? 2.2.2 Identify the risks that need to be addressed.
2.2.3 What would recommend Marcus i does before finalising the project plan and communicating it to her stakeholders?