The following represents a project that should be scheduled using CPM: b. What is the critical path? B-E-G-H A-D-F-H A.C-F-H A⋅D−G−H c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. b. What is the critical path? B-E-GH A.D-F.H A.C.F.H A.D.G.H ​
c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimel places. d. What is the probability of completing this project within 16 days? Note: Use Excel's NORM.S.DIST function to find the correct probobility for your computed Z value. Do not round intermediate colculotions: Round Z value to 2 decimal ploces ond final answer to 4 decimal ploces.