Develop a chase plan that matches the forecast, and compute the total cost of your plan over time if the cost is $60 per hundred bolts. If the forecast is 500 bolts in month one, 600 bolts in month two, and 700 bolts in month three, what is the total cost for the three months?
a) $1,800
b) $2,400
c) $2,700
d) $3,000