A project you are managing had a starting budget of 180,000 USD and an expected duration of 1 year and 3 months. The work and budget are spread equally over the duration.
You are currently 8 months into the project, the work is on schedule, and so far you have spent 102,000 USD.
What is the cost variance of the project?