QUESTION 2.2 Description: You are a project manager overseeing the design and programming of a new software system to replace the old manual material requirements suite that was used by the programme office. (Note: see yourself as an IT project manager) The activity table below was compiled with the entire team and the customer is awaiting the final schedule and costs to prepare for the budgetary provision of the entire project. You are the project manager (PM). Peter is the System Software Specialist and reports to you. He also supervised the User Requirement Specifications and confirmed the budget. Fani is the Application Software specialist and also reports to you. He knows all the licensing requirements and the programming staff report to him. Annie is in charge of the licensed programming team and Jan is responsible for the client development team. Both Annie and Jan report to Fani. Andrew is the AGILE PM expert that does team building and team “scrums”. Andrew reports directly to you as the PM. Sifiso is in charge of the development server where all the programming integration is thoroughly tested before commissioning. Sifiso reports to Peter, who also oversees the quality control. Study the Activity Table below and execute the following: Activity Table ID DESCRIPTION PREDECESSOR Resources TIME