Station A's primary bus is connected to Station B's primary bus by a 230 kV transmission line. Both stations have a 100 MVAR switchable shunt capacitor bank currently offline. The SOL on this line is 350 MVA. The System Operator notices that the flows on the line are as follows.
345 MW from Station A towards Station B
100 MVAR from Station B towards Station A
What should the system operator do to return the system to its operating limits?
A) Energize a Reactor Bank at station A
B) Place the capacitor bank on-line at Station B
C) Place the capacitor bank on-line at Station A
D) Remove the transmission line from service