Batch process requires the following operations to be completed in sequence: 3 hr of mixing, 5 hr of heating, 4 hr of reaction, 7 hr of purification, and 2 hr of transfer.
When the five operations are carried out in vessels U1, U2, U3, U4, and U5, respectively, determine the cycle times, and construct Gantt charts corresponding to the zero-wait, intermediate storage, and unlimited intermediate storage inventory strategies.