The software project is in its seventh month of work. The Project Duration is 8 months. The Project manager estimates that the project is at least 3 months behind its schedule. She believes the main reason for the delay is:
a) Lack of funding
b) Poor project management
c) Technical difficulties
d) Unforeseen external factors