yuselis9911 yuselis9911 08-03-2024 Computers and Technology contestada A project network has the following paths. How much slack does path ABEGHI have? Path Duration ABDFHI 41 ABEFHI 48 ABEGHI 55 ACGHI 40 a) 0 days b) 7 days c) 14 days d) 17 days