During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain feedback from on project deliverables. What should the project manager do?
1) Use networking skills to approach the stakeholder.
2) Update the stakeholder engagement plan for the stakeholder.
3) Ask the project sponsor to arrange a meeting with the stakeholder.
4) Share a template with the stakeholder to receive feedback on deliverables.