Assume you are the manager of a shop that assembles power tools. You have just received an order for 52 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws follows:


Item Lead Time (weeks) On Hand Components
Saw 2 15 A(2), B(1), C(4)
A 1 10 E(3), D(1)
B 2 5 D(2), F(3)
C 2 65 E(2), D(2)
D 1 20
E 1 10
F 2 30

Develop the material requirements plan for component E using lot-for-lot ordering for all items. (Leave no cells blank - be certain to enter "0" wherever required.)