To help determine scope in a traditional project, the team would develop a work breakdown structure (WBS). In Scrum, teams instead use product and sprint backlogs to develop a high-level description of the work that needs to be done. A traditional Gantt chart can still be useful in agile projects, however. Prepare a Gantt chart for the health-care app project; you can use Figure 3-6 as a guide if necessary. You can download freeware from the Internet that enables you to create the Gantt chart, or you can create it with pen and paper. Your Gantt chart should incorporate all the new information and milestones you developed in the preceding tasks for Part 3.