In order to be useful as schedule building blocks, activities should have certain characteristics. Which of these is NOT a characteristic that an activity should have?
a. Output can be independently verified and measured.
b. Work component at the lowest level of the WBS, for which cost and duration can be estimated and managed.
c. Resources, cost, and time can be estimated exclusively.
d. Defined start and end points