a person hour is a unit of measure representing one person working for one hour. A construction foreman estimates it will take 2880 person-hours to build a new library.If 12 workers are scheduled to work on the project at the same time, how many hours will it take to complete the project

Respuesta :

It will take about 240 hours to complete the project, I am very sorry if my answer is incorrect