steamline bicycles produces two kinds of bikes, mountain bikes and road bikes. it takes 4 hours to build a mountain bike and 3 hours to build a road bike. the company has 21 employees, each with a 40 hour work week. due to demand, they must produce at least 250 total bikes each week. if they profit $ 75 on each mountain bike and $ 60 on each road bike, how many of each type should they produce in a week to maximize their profit?

Respuesta :

Answer:

To maximize the profit, the number of mountain bikes to be produced each week is 250 and the number of road bike to be produced each week is 0.

Step-by-step explanation:

Let, the number of mountain bike = x and number of road bike = y.

As minimum number of bike to be produced each week is 250.

Thus, x + y ≥ 250.

Also, mountain bike takes 4 hours to build and road bike takes 3 hours to build each week.

As, the employees work for 40 hours each week.

Thus, we get, 4x + 3y = 40.

Now, the objective is to maximize the profit given by z = 75x + 60y.

Thus, we get the system,

z = 75x + 60y

4x + 3y = 40

x + y ≥ 250

Using 'zero test' i.e. substituting ( 0,0 ) in the equation 2 and 3, we get that,

4x + 3y = 40 ⇒ 0 = 40, which is not true

x + y ≥ 250 ⇒ 0 ≥ 250, which is not true.

So, both the equations will have the solution region away from the origin as seen in the graph.

Also, the solution points are given by ( -710,960 ), ( 0,250 ) and ( 250,0 ).

Substituting these points in the objective function z = 75x + 60y, gives,

Points             z = 75x + 60y

( -710,960 )     z = 75 × (-710) + 60 × 960 = 4,350

( 0,250 )          z = 75 × 0 + 60 × 250 = 15,000

( 250,0 )          z = 75 × 250 + 60 × 0 = 18,750

So, we see that the maximum value of the profit defined by z = 75x + 60y is $18,750 at the point ( 250,0 ).

Hence to maximize the profit, the number of mountain bikes to be produced each week is 250 and the number of road bike to be produced each week is 0.

Ver imagen wagonbelleville