Answer:
(C) $464,120
Explanation:
The computation is shown below:
First, Calculate the predetermined overhead rate per hour which equals to
= (Estimated Overhead cost ÷ estimated machine hours)
= ($492,000 ÷ 30,000 hours)
= $16.4 per hour
So, the applied overhead equals to
= Predetermined overhead rate per hour × actual machine hours
= $16.4 per hour × 28,300 hours
= $464,120