Respuesta :
Answer:
0.0359
Step-by-step explanation:
Data provided:
mean values of three independent times are 15, 30, and 20 minutes
the standard deviations are 2, 1, and 1.6 minutes
Now,
New Mean = 15 + 30 + 25 = 65
Variance = ( standard deviation )²
or
Variance = 2² + 1² + 1.6² = 7.56
therefore,
Standard deviation = √variance
or
Standard deviation = 2.75
Thus,
Z-value = [tex]\frac{\textup{60 - 65}}{\textup{2.75}}[/tex]
or
Z-value = - 1.81
from the Z-table
the Probability of Z ≤ -1.81 = 0.0359
The probability that it takes at most 1 hour of machining time to produce a randomly selected component is 0.0344 approx.
What is the distribution of random variable which is sum of normal distributions?
Suppose that a random variable X is formed by n mutually independent and normally distributed random variables such that:
[tex]X_i = N(\mu_i , \sigma^2_i) ; \: i = 1,2, \cdots, n[/tex]
And if
[tex]X = X_1 + X_2 + \cdots + X_n[/tex]
Then, its distribution is given as:
[tex]X \sim N(\mu_1 + \mu_2 + \cdots + \mu_n, \: \: \sigma^2_1 + \sigma^2_2 + \cdots + \sigma^2_n)[/tex]
For the given case, if we take:
- [tex]X_1 =[/tex]Time taken by first operation
- [tex]X_2 =[/tex]second operation
- [tex]X_3 =[/tex]operation
Then, by the given data we get:
[tex]X_1 \sim N(15, 2^2)\\X_2 \sim N(30,1^2)\\X_3 \sim N(20, 1.6^2)[/tex]
(since standard deviation's square is variance)
Then, Let X denotes the total time taken by all 3 operations to manufacture the product, then:
X = [tex]X_1 + X_2 + X_3[/tex] = Total time taken for manufacturing
Then, the needed probability is:
[tex]P(\text{total time is at max 1 hour = 60 minutes}) = P(X \leq 60)[/tex] (as all other random variables are doing calculating in minutes).
Since it is given that all three operations are independent, thus, we get the distribution of X is given as:
[tex]X \sim N(15 + 30 + 20, 2^2 + 1^2 + 1.6^2)\\\\X \sim N(65, 7.56)[/tex]
Here
[tex]\mu = 65,\\\sigma^2 = 7.56[/tex]
Now using the conversion to standard normal variate and the z-tables to calculate the needed probability, we get:
[tex]Z = \dfrac{X - \mu}{\sigma} = \dfrac{X - 65}{\sqrt{7.56}} \approx \dfrac{X - 65}{2.749}[/tex] (positive root since standard deviation is a non negative quantity)
The needed probability becomes
[tex]P(X \leq 60) = P(Z \leq \dfrac{60 - 65}{2.745}) \approx P(Z \leq -1.82)[/tex]
From the z-tables, we get the p value for Z = -1.82 is p = 0.0344
(p value for Z = z shows [tex]P(Z \leq z)[/tex] )
Thus, we get:
[tex]P(X \leq 60) \approx P(Z \leq -1.82) \approx 0.0344\\P(X \leq 60) \approx 0.0344[/tex]
The probability that it takes at most 1 hour of machining time to produce a randomly selected component is 0.0344 approx.
Learn more about standard normal distribution here:
https://brainly.com/question/10984889