Answer:
The predetermined overhead rate for the recently completed year was $25.33
Explanation:
The formula to compute the predetermined overhead rate is shown below:
Predetermined overhead rate = (Total estimated manufacturing overhead) ÷ (estimated direct labor-hours)
where,
Total estimated manufacturing overhead = Estimated total fixed manufacturing overhead + estimated variable manufacturing overhead rate × estimated labor hours
= $1,230,440 + $3.12 × 55,400 hours
= $1,230,440 + $172,848
= $1,403,288
Now put these values to the above formula
So, the rate would equal to
= $1,403,288 ÷ 55,400 hours
= $25.33