Bill Builder entered into a contract with Carl's Carpets to supply him with the carpeting he needed to complete the renovation of Famous Restaurant. When Carl did not deliver the carpeting on the contract date, Bill had to find similar carpeting from a different vendor for 5 a yard more than he would have paid to Carl. There was a time is of the essence clause in Bill's contract with Famous Restaurant. Bill was to lose 300day for each day after the contract date that he was late in finishing the renovation. The 300 day represented the profit Famous Restaurant would lose each day it was not in operation. Bill told Carl about this clause, impressing on Carl the need for him to deliver the carpet on time. Bill finished the renovation three days after the contract date. The delay was due solely to Carl's failure to deliver the carpet on time. Bill can recover the 900 he lost from Carl as ___________ damages.

Respuesta :

Answer:

consequential damages

Explanation:

According to my research on different types of law suits, I can say that based on the information provided within the question Bill can recover the 900 he lost from Carl as consequential damages. These are damages have happened because of one party's failure to meet a certain deadline or contractual obligation and can be proven in court. Therefore since Bill can prove that he lost the 900 because of Carl's negligence he will most likely win that case.

I hope this answered your question. If you have any more questions feel free to ask away at Brainly.