Heidi makes rag quilts. Each child-sized quilt contains 4.25 yards of flannel priced at $4.80 per yard and thread costing $0.24 per quilt. Heidi also allows 0.10 yards of fabric for waste per quilt. Direct labor for each quilt requires 2 hours of cutting and 4 hours of sewing. Cutters' direct labor rate is $7.25 per hour, and sewers' direct labor rate is $8.50 per hour. Rest periods of 0.01 hours per quilt are allowed for both sewers and cutters, with an additional 0.02 hours per quilt allowed for machine downtime. What is the standard direct materials cost per quilt?
A. $21.12
B. $21.95
C. $19.50
D. $17.80

Respuesta :

Answer:

Direct material cost per quilt will be

Flannel 4.25*4.80 = 20.4

Fabric wasted 0.10*4.80 = 0.48

Thread 0.24 per quilt

20.4+0.48+0.24=21.12

So A is the correct answer

A material utilized for manufacturing and constituting a significant percentage of a product is referred to as direct material. Standard Cost for Direct Material is a predetermined cost for direct material. So, option A is the correct answer.

What is the standard direct materials cost (SDMC)?

[tex]\text{Direct material cost per quilt will be}[/tex]

[tex]\text{Flannel} = 4.25 \text{ x }4.80 = 20.4[/tex]

[tex]\text{Fabric wasted} = 0.10 \text { x } 4.80 = 0.48[/tex]

[tex]\text{Thread} = 0.24 \text{ per quilt}[/tex]

[tex]\text{SDMC} = 20.4+0.48+0.24=21.12[/tex]

For more information about Standard direct materials, refer below

https://brainly.com/question/26210585