Direct material cost per quilt will be
Flannel 4.25*4.80 = 20.4
Fabric wasted 0.10*4.80 = 0.48
Thread 0.24 per quilt
20.4+0.48+0.24=21.12
So A is the correct answer
A material utilized for manufacturing and constituting a significant percentage of a product is referred to as direct material. Standard Cost for Direct Material is a predetermined cost for direct material. So, option A is the correct answer.
What is the standard direct materials cost (SDMC)?
[tex]\text{Direct material cost per quilt will be}[/tex]
[tex]\text{Flannel} = 4.25 \text{ x }4.80 = 20.4[/tex]
[tex]\text{Fabric wasted} = 0.10 \text { x } 4.80 = 0.48[/tex]
[tex]\text{Thread} = 0.24 \text{ per quilt}[/tex]
[tex]\text{SDMC} = 20.4+0.48+0.24=21.12[/tex]
For more information about Standard direct materials, refer below