Answer:
3.
Explanation:
We start calcualting the factor for heavy-vehicle, that is,
[tex]f_{HV} = \frac{1}{1+P_T(E_T-1)+P_R(E_R-1)}[/tex]
[tex]E_T = 2.5[/tex] for rolling terrain, so, replacing,
[tex]f_{HV} = \frac{1}{1+0.18(2.5-1)+0}[/tex]
[tex]f_{HV} = 0.7874[/tex]
We calculate the number of lanes by using the relation as follow:
[tex]N=\frac{V}{\upsilon_p PHF f_{HV} f_p}[/tex]
[tex]N=\frac{2700}{1915*0.88*0.7874*1}[/tex]
[tex]N= 2.035[/tex]
In this way the necessary number of lanes is 3.
Note: To calculate [tex]\upsilon_p[/tex] you need to consult the Exhibit 23-2
in 'Highway capacity Manual' for 55mph and the LOS D criteria.