Answer:
False
Explanation:
Budgeted of factory overhead cost = $600,000
Budgeted machine hours = 100,000 hours
Budgeted units to be produced = 200,000 units
Zorn's plantwide factory overhead rate:
= Budgeted of factory overhead cost ÷ Budgeted units to be produced
= $600,000 ÷ 200,000
= $3 per unit
Therefore, the answer given in question is false.