Answer:
Total cost= $4,900
Explanation:
Giving the following information:
Each member of the project is assigned an overhead charge of $100/week. What would the fully loaded cost of labor be for an employee, given that she is assigned to the project for 280 hours at $15/hour? Hint: The hours that the employee works (280 hours) would equate to 7 weeks.
Total cost= direct labor + allocated overhead
Total cost= 280*15 + 100*7= $4,900