Conrad Construction Corp. has a $20 million contract to construct a building. The company estimates gross profit of $4 million. During the current year, the company incurred $2 million of costs on the contract. Under the percentage-of-completion method, how much will Conrad Construction Corp. report as revenue in the current year?