In a garments factory, a part requires 0.10 hours of labor per unit in Work Center B and 1 hour of setup time. The planned order release (order size) for a week is 2000 units. Which of the following is the capacity requirement for a week at Work Center B?a. 101
b. 151
c. 251
d. 201