Answer:
The correct answer is B.
Explanation:
Giving the following information:
During April, direct labor cost totaled $15,000 and direct labor cost was 30% of prime cost. If total manufacturing costs during April were $79,000.
Manufacturing cost= direct material + direct labor + manufacturing overhead
Prime cost= direct material + direct labor
50,000= DM + 15,000
Direct material= 35,000
79,000= 35,000 + 15,000 + manufacturing overhead
manufacturing overhead= 29,000