Answer:
d) $5100
Explanation:
Simply calculate per unit labor cost.
This can be done as follows
Per unit labor cost = hours used by unit * per hour rate
So, Cost = 0.1 * 8.50 = $0.85/ labor cost per unit produced.
Now multiply per unit cost with total units budgeted
Total Labor budget = 6000 * 0.85 = $5,100