Answer:
The cost of completed jobs transferred from Work in Process to Finished Goods during the year was a)$504,000
Explanation:
The cost of completed jobs transferred from Work in Process to Finished Goods during the year = Credits Work in Process = Work in Process Bal. 1/1 + Debits Work in Process - Work in ProcessBal. 12/31
Maysonet Corporation provided they completed T-account summary for the past year: Work in Process Bal. 1/1 $18,000 Debits $520,000 Bal. 12/31 $34,000
The cost of completed jobs transferred from Work in Process to Finished Goods during the year = $18,000 + $520,000 - $34,000 = $504,000