LO 6.3A company calculated the predetermined overhead based on an estimated overhead of $70,000, and the activity for the cost driver was estimated as 2,500 hours. If product A utilized 1,350 hours and product B utilized 1,100 hours, what was the total amount of overhead assigned to the products?

$35,000
$30,800
$37,800
$68,600