Answer:
Please see the naswer below
Explanation:
Activity-based costing ABC is a method for assigning costs to products, services projects, tasks, or acquisitions, based on the Activities that go into them and the Resources consumed by these activities. Following is the proper order of tasks in an ABC system
1. Identify the primary activities and estimate a total cost pool for each.
2.Select an allocation base for each activity.
3.Calculate an activity cost allocation rate for each activity.
4. Allocate the costs to the cost object using the activity cost allocation rates.