BEFH is the critical path of this project with total duration of 16 weeks
Explanation:
Activity Predecessor Time
A - 1
B - 4
C A 1
D B 5
E B 2
F C,E 7
G D 2
H F,G 3
First we draw the network diagram, as shown in the attachment, according to the predecessors of each activity.
Critical activties have zero float (i.e, difference in values of final and initial start or finish of activty)
Critical Path: BEFH
Length: As shown in figure the length of critical path is 16 weeks. In other words, it takes 16 weeks to complete the project.

Answer:
Explanation:
The activities on the critical path are BEFH
The length of the critical path is 16 weeks