Answer:
overhead rate will be equal to $62 per machine hour
So option (B) will be correct option
Explanation:
We have given total overhead for the current year will be $15500000 with total 250000 machine hours.
And actual overhead is $16000000 and actual machine hour is 330000 hours
We have to find the overhead rate based on machine hour
Overhead rate is the ratio of estimated overhead to estimated total machine hours
So overhead rate [tex]=\frac{15500000}{250000}=62[/tex] $ per machine hour
So overhead rate will be equal to $62 per machine hour
So option (B) will be correct option