A state highway was constructed over wetlands. The state obtained a permit to fill the existing wetlands in accordance with the provisions of the Clean Water Act in 1972, and agreed to create another wetland. This trade-off approach to addressing an environmental issue is known as__________.

Respuesta :

Answer:

Environmental mitigation

Explanation:

Environmental migitation is related environmental industry to describe  impacts to the  wetland, endangered species, archeological site, paleontological site or historic structure.

This  Act mainly focus on action of reducing the severity, seriousness, or painfulness to the environment.

According Clean Water Act in 1972, they agreed to create a another wetland for state highway which was constructed over wetlands.