The critical path is A-B-C, with a duration of 15 minutes.
Explanation:
- The critical path is A-B-C, with a term of 15 minutes. You don't need to be knowledgeable in computer lingo to make sense of this one (as I made sense of it absent a lot of data on that half of the condition). Here's the manner by which I made sense of this.
- The main thing I saw was that "predecessor" was utilized, which implies something precedes the other thing. That provided me the primary insight that A precedes B and C, and that B must precede C. Then, I just included the term times for the three ways, which allowed me 15 minutes.
The critical path and time duration is A. The critical path is A-B-C, duration is 15.
Based on the information given, the critical path is the longest sequence of tasks that must be completed in order to successfully conclude a project.
It can be depicted that the critical path is A-B-C, and the duration will be the addition of 4, 3 and 8 which is 15.