Answer:
c. planning schedule management
Explanation:
The first process involved in project time management is planning schedule management. The sequence of the steps in project time management are outlined below;
Planing schedule management
Defining activities
Sequencing activities
Estimating activity resources
Estimating activity durations
Developing schedule
Controlling schedule