Respuesta :

bogadu

Answer:

c. planning schedule management

Explanation:

The first process involved in project time management is planning schedule management. The sequence of the steps in project time management are outlined below;

Planing schedule management

Defining activities

Sequencing activities

Estimating activity resources

Estimating activity durations

Developing schedule

Controlling schedule