Respuesta :
Answer:
Activity Rate for Setup = $18
Explanation:
Given
Activity Total Activity-Base Usage Budgeted Activity Cost
Setups 10,000 $180,000
Inspections 24,000 $120,000
Assembly (dlh) 80,000 $400,000
Activity Rate is calculated by: Budget Activity Cost/Activity Base Usage
Where Activity Base (for Setup) = 10,000
Budget Activity Cost = $180,000
So, Activity Rate for Setup = $180,000/10,000
Activity Rate for Setup = $18
Hence, the calculated activity Rate for setups is $18
Answer:
b.$18.00
Explanation:
The rate of activity can be estimated by using the total number of activity and the cost incurred. This is normally used to show the progress of the specific activity and it can either positive or negative. In this problem, the activity rate of setups is equivalent to $180000/10000 = $18. Therefore, the correct answer is option b.