Respuesta :
Answer:
Recoder point =625 units
Explanation:
Detailed explanation of answer is given in the attached file.

Reorder point of the given question is 430 units
Computation of average lead time;
Average lead time = [20 + 10] / 2
Average lead time = 15 days
Computation of safety stock
Safety stock = [Maximum Daily Use × Maximum leads days] - [Average daily use - Average lead time]
Safety stock = [(25)(20)] - [(3500/250)(15)]
Safety stock = 500 - [210]
Safety stock = 290 units
Reorder point = [(Average daily use)(Minimum lead time)] + Safety stock
Reorder point = [(3500/250)(10)] + 290
Reorder point = 430 units