Answer:
Machine C
Explanation:
The computation of the expected benefit is shown below:
For Machine A
= $45,000 × 90%
= $40,500
For Machine B
= $80,000 × 50%
= $40,000
For Machine C
= $60,000 × 75%
= $45,000
If we see the expected benefit of each machine so we can say that the Machine C has the highest benefit generated from the available ones