A __________ shows their appropriate sequence and defines the dependent relationships indicating how the activities need to be performed to accomplish the overall project work scope and produce the deliverables.

Respuesta :

Answer: Network Diagram.

Explanation:

When carrying out a project, a network diagram is a chart that shows the different tasks to be done in a project and the way the task are connected, with the aim of ultimately completing the project. The network diagram represents the task to be completed as boxes and connecting lines are drawn to show connection between tasks