Answer:
$900,000
Explanation:
Given that,
Activity rate for Machining = $200 per machine hour
Total machine hours = Product V3 + Product G8
= 1,500 + 3,000
= 4,500
Total number of batches = 71
Total cost of Machining:
= Total machine hours × Activity rate for Machining
= 4,500 machine hours × $200 per machine hour
= $900,000